Final Surface Paving Phase 2

Below is a message from “Marty Collier” in regards to paving for Phase 2 of our development.

Dear Homeowner,

Paving has not gone as expected. To date, only Alysium Court has been paved and Heartwood Terrace & the private drive off of Achilles Lane prepped for paving.

Below is the revised paving schedule, weather permitting.

1) Friday 6/30/17 they will pave Heartwood Terrace and the private drive off of Achilles Lane.

2) Wednesday 7/5/17 they will prep Heartwood Drive and Achilles Lane for paving.

3) Thursday 7/6/17 pave Heartwood Drive and Achilles Lane.

4) Friday 7/7/17 finish paving Heartwood Drive and Achilles Lane.

I apologize for any inconvenience that this may have caused. Thank you in advance for your cooperation.

Marty Collier
Land Development Construction Manager

Any questions please feel free to send an e-mail message to contact@preserverockcreek.org.

Please see the PDF below showing the streets to be paved highlighted in yellow.